A Quieter Market, Costlier Builds: Why Tender Prices Are Rising Anyway
Turner & Townsend's Q4 2026 UK Market Insight, published last week, confirms something we are seeing in live tender returns: the old assumption that a quiet market is a cheap market no longer holds. As Stephanie Marshall, the firm's UK real estate cost management lead, put it: "A quieter overall construction market no longer means a cheaper environment to build."
The headline numbers look weak. New orders are down 18.1% year-on-year and sit below their long-term average. Overall new-work output rose just 0.4% in Q2 2026 and remains 6.1% below the same quarter last year. Private commercial (+2%), infrastructure (+1.9%) and private housing (+1.1%) grew modestly, offset by falls in public housing, public non-housing and private industrial work.
Why Prices Rise While Orders Fall
Against that backdrop, Turner & Townsend has raised its tender price forecasts for the first time in two years — 3.75% annual growth for real estate in 2026 and 2027 (up from 3.5%) and 5.25% for infrastructure (up from 5%). The drivers are the ones QS teams have been tracking all year: tariffs, including the July 2026 steel measures, commodity and energy prices, and concentrated competition for labour and suppliers in the busy regions and sectors — data centres, energy and major infrastructure. Steel-intensive schemes face the sharpest increases.
Contractor behaviour reinforces the shift. Two-thirds of contractors surveyed said protecting profit margins now outranks growing revenue. They are being selective, and subcontractors flagged difficult contract conditions, poor design information and slow approvals as reasons to walk away. BCIS's updated five-year forecast points the same direction: building costs up 14% and tender prices up just over 14% by 2031.
What This Means for Clients
The practical consequence is that procurement quality now moves price as much as market volume does. Turner & Townsend notes projects attract stronger bids where clients provide clear designs, define scope precisely and offer balanced terms. In London, where detailed planning approvals fell 29% year-on-year and only 2,103 private homes started on site in Q1 (Molior), schemes that do reach market are competing for a supply chain that has no shortage of better-behaved clients to work for.
Practical Steps Now
- Re-baseline cost plans now. If your 2026–27 benchmarks assume 2–3% inflation, they are behind the market. Test viability at 3.75% real estate / 5.25% infrastructure and stress steel-heavy packages separately.
- Invest in tender quality. Complete design information, early supplier engagement and fair contract terms are converting directly into keener bids — the cheapest lever available in this market.
- Watch escalation risk allocation. Contractors are pricing defensive risk loads into preliminaries and float. A well-drafted fluctuation clause can be cheaper than a contractor's worst-case escalation premium.
- Check regional and sector context. Averages mask wide variation; benchmark against your actual supply market, not the national figure, in line with RICS cost prediction guidance.
For funders reviewing development appraisals, and for contractors deciding which work to chase, the message is the same: volume is soft, but pricing power has shifted to the supply chain. Budget for it.
Sources
- Turner & Townsend, UK Market Insight, Q4 2026 (reported by Construction News, 12 November 2026)
- BCIS five-year construction industry forecast (update reported 7–8 November 2026)
- Molior London, Q1 2026 private housing starts
- RICS guidance on cost prediction and benchmarking
Construction Insights & Cost Benchmarking — Free
Practical construction commentary and cost overviews — delivered free, four times a year.
Related insights
→ Construction Forecast Winter 2026–27 → Steel Tariffs 2026: Cost Impact for UK Construction → New Orders Fall 12%: Q2 2026 Pipeline Data