Adjudication: A Practical Guide to the 28-Day Route
Adjudication is the construction industry's default dispute resolution machine — introduced by the Housing Grants, Construction and Regeneration Act 1996 and hardened by the Local Democracy, Economic Development and Construction Act 2009. It exists to keep money flowing while a project runs, not to produce the final word. Yet for all its familiarity, the queries we receive suggest many contractors and employers still meet it unprepared. This guide sets out the practical sequence.
1. The statutory right
Any contract for construction operations within the Act's scope must include adjudication provisions meeting certain minimum standards — or the statutory Scheme for Construction Contracts applies by default. Either way, a party has the right to refer a dispute "at any time". The referring party controls the trigger: no notice period, no permission needed.
2. The referral and the 28 days
The timetable runs from the referral notice. The adjudicator must reach a decision within 28 days of referral, unless the referring party agrees to an extension. That single constraint shapes everything: the referring party arrives with its case fully documented, and the responding party often has days, not weeks, to respond. Practical consequences:
- Prepare before you refer. The referral is the one document the timetable favours — evidence, calculation, and contract basis should be complete on day one.
- Responding? Ask for time early. Extensions are commonly granted for proportionate requests made immediately, almost never for late ones.
- Decide what "the dispute" is. A referral framed around a single crystallised issue moves faster and cleaner than a rolling account.
3. The adjudicator's powers
The adjudicator may take the initiative in ascertaining facts and the law — meeting the site, directing submissions, and appointing experts — but must act impartially and observe the rules of natural justice. The two most common challenges to decisions are jurisdiction (was there a dispute at all? is this the same dispute already decided?) and natural-geometry breaches (deciding on a basis neither party advanced without giving them a chance to comment). Both are avoidable with careful process management.
4. Enforcing (or resisting) the decision
The decision is binding until the dispute is finally resolved, and the court's default position is summary enforcement. The narrow grounds of resistance were confirmed by the Technology and Construction Court in PC Harrington v Systech and refined through the subsequent line of authorities: breaches of natural justice that materially affected the result, jurisdictional failure, or (rarely and only per the Supreme Court in Aspect Contracts v Higgins) a simple slip correction window before enforcement. An unsuccessful respondent's realistic strategy is usually to pay and preserve its position for arbitration or litigation.
5. Costs and practical value
Each party normally bears its own costs of the adjudication and shares the adjudicator's fees — which makes the process proportionate for payment disputes (the majority of referrals) and strategic for definitional issues that will govern a final account. The practical value is cash flow and time: a decision in weeks that holds until final resolution.
What we do
NorthEight prepares and defends adjudication referrals — payment disputes, final account positions, extension-of-time determinations — and provides the quantum support that makes a 28-day timetable workable. If a payment dispute is crystallising on your project, the earlier the referral preparation starts, the stronger the position. Get in touch.