Liquidated Damages
Liquidated damages — LDs — are the pre-agreed sum payable by the contractor for failing to complete by the completion date, operating as the employer\'s exclusive delay remedy provided they represent a genuine pre-estimate of loss.
LDs are a deal about risk, priced at tender. The employer buys certainty — no proving actual loss — and the contractor buys a ceiling. The number only survives challenge if someone genuinely tried to estimate delay cost when the contract was made; a figure plucked to frighten is a penalty and unenforceable.
The interplay with extensions of time is where the money lives. No extension, and LDs accrue to the last day; extension granted, and the LD window moves with the completion date. The notices, the programme records and the arithmetic of the adjustment decide more disputes than the rate itself.